Young Epilepsy is the only UK charity dedicated to creating better lives for children and young people with epilepsy and related conditions. With over 120 years expertise, they provide world class diagnosis, assessment and re-habilitation for children and young people with epilepsy. They also undertake research into the condition and how it can be treated. St Piers School and College provide outstanding, highly specialised education for young people with neurological conditions such as epilepsy. Set in stunning grounds near Lingfield, it offers the latest facilities to help students grow in confidence and learn independence.
Download Project Report HereFollowing on from an initial LitmusFM facilities services review of the Young Epilepsy Lingfield facilities, the senior management team requested that LitmusFM provided external Project Management support toco-ordinate and manage their proposed capital works programme, for the refurbishment of special educational needs pupil accommodation blocks to the Young Epilepsy estate.
Our approach was to provide an experienced team that could fully support the proposed refurbishment project, with a remit to specifically undertake the following activities:
The Young Epilepsy existing condition survey schedules provided a solid basis for the development and production of a schedule of refurbishment works.
There was however a requirement for some additional information to be obtained for the tender, and this was generated from a site inspection and site visits.
A full tender specification was then produced to support the schedule of works packages.
We also arranged for marked-up layout plans to be provided with the tender, which assisted in ensuring the tenderers understood the layout and the location of the works, and any access/ space restrictions. We then carried out an evaluation to assess the technical requirements for any replacement plant and equipment. For example, was there a requirement to replace solely with ‘like with like’ or was there a requirement to provide upgrades to the performance and control arrangements.
We then produced the formal tender programme and the project management arrangements. This included supplier selection and theLitmusFM contract management arrangements to support the work packages, which included:
When we were awarded the works, the programme was already three months overdue. Using our experienced Project Manager, we managed to deliver the tender and construction on time and at the budget specified.